Urgent Gas Works notice!
Published Friday 19th March 10
National Grid Gas will be undertaking urgent mains replacement work in Parsonage Lane and Holtwhites Hill during the next few weeks.
PARSONAGE LANE approximated duration 8-10 weeks
Week starting (subject to change) - 14/03/2010
Approx. duration - 1 week
Detail of works - North side of Parsonage Lane in footway. Nunns Road (North) closure for 2 days to facilitate road crossing.
Week starting (subject to change) - 21/03/2010
Approx. duration - 2 weeks
Detail of works - South side of Parsonage Lane in carriageway. Nunns Road (South) closure to make connection. Insert pipe along carriageway towards Chase Side Avenue near kerb (two way traffic maintained).
Week starting (subject to change) - 05/04/2010
Approx. duration - 2 weeks
Detail of works - 3-way lights at Parsonage Lane jw Chase Side Avenue (details t.b.c at site meeting). Traffic management to be reset for Monastery Gdns.
Week starting (subject to change) - 19/04/2010
Approx. duration - To be Confirmed
Detail of works - Insert away from Chase Side Ave towards Silver Street in c/w. 2-way lights to be used as necessary (identified at future site meeting).
Week starting (subject to change) - To be Confirmed
Approx. duration - To be Confirmed
Detail of works - Site meeting to be held to discuss traffic management for connection work at Parsonage Lane jw Chase Side. 4-way lights likely.
HOLTWHITES HILL approximated duration 8 week following on from Parsonage Lane
Week starting (subject to change) - To be Confirmed
Approx. duration - 8 weeks
Detail of works - These works involve mains replacement on both sides in the footway but will impact the carriageway to manage pedestrian traffic and road crossings / connections. Traffic management will be required where minimum width can not be maintained (details to be confirmed at site meeting with police and buses).